At the beginning of a project, there’s often an assumption that the information available is enough to get going. The drawings look reasonable. The scope feels clear. The programme is tight, but achievable.

What we’ve learned over time is that gaps in information before the work starts affect certainty of programme, cost and quality.

We learned that lesson early on with a recent project. It looked like a relatively small job with a short programme. Some of the information was light, but it felt manageable at the time. There was no QS or structural engineer involved, and certain inputs hadn’t been fully developed.

As the project progressed, those gaps became harder to ignore. Decisions took longer. The works became more reactive than planned. The programme came under pressure, and costs started to creep.

It wasn’t a dramatic failure but it was just inefficient. And it was avoidable.

“It felt small at the start, but the lack of planning caught up with us.” - Cathal Grant, CEO

That project changed how we approach things. Now, if key information isn’t in place at the beginning, we’ll challenge it. Not to slow things down, but because experience tells us where those gaps lead.

Question assumptions

Another common issue is assuming that what’s on the tender information and as-built information fully reflects what exists in the building.

Usually, everyone starts out believing that’s the case. What we’ve found is that it isn’t always true. Changes get made over time, records aren’t always updated, and buildings often evolve in ways that aren’t fully captured.

If those differences aren’t picked up early, they tend to surface once work is underway, when ceilings are opened or walls are stripped back. At that point, options are limited and pressure increases quickly.

That’s why we now spend time upfront making sure we understand what’s actually there before starting work. On larger projects, that might involve detailed point cloud surveys.

The aim is always to mitigate risk posed by inaccurate or incomplete information.

Previous Grant Fit Out projects.

Programme certainty isn’t just about agreeing an end date.

A fit out might be scheduled for five or six weeks, but that doesn’t mean everything needed for it can be delivered within that timeframe. Some items have lead times that are longer than the programme itself.

Fire doors are a good example. Bespoke joinery is another. These elements often need design input from suppliers, followed by approvals and sign-off, before anything can be ordered.

“You can have a short programme, but if critical items won’t arrive until after it’s meant to finish, the programme isn’t realistic.” - Cathal Grant, CEO

That’s why procurement and design schedules matter just as much as the overall programme. Allowing time for those steps doesn’t slow a project down. Ignoring them usually does.

Predictability and price

Clients will sometimes be presented with a cheaper option elsewhere. That doesn’t automatically mean it’s wrong, but it often means certain things haven’t been fully allowed for. Which means lots of variations.

Design coordination, technical input and supplier support all take time. If those pieces aren’t there, the impact tends to show up later through changes, delays or compromises on quality.

The role of experience and decision-making

Projects run more smoothly when experienced people are involved from the client side. Fact. When decisions can be made quickly and issues are addressed early, challenges don’t have time to grow.

Fit-out programmes are always tight. It takes strong leadership, planning and management  to drive them over the line - contractor working with design team and client - clear communication and a collaborative, solutions-focused approach.

A question worth asking early

Looking back across projects that have gone well, a pattern emerges. They weren’t perfect, and they still had challenges, but they were set up properly from the start.

Before a fit out begins, it’s worth taking a moment to ask a simple question:

Am I giving my contractor everything they need to be successful?

Because when that answer is clear at the beginning, the chances of a predictable outcome are much higher.

Start the conversation HERE

Cathal Grant | CEO

Cathal founded Grant Fit Out in 2008. He has 20 years’ experience working across the construction and fit-out sector and holds a First Class Honours degree in Architecture and the Built Environment from the University of Ulster. As CEO, Cathal is responsible for the overall leadership and strategic direction of the business, drawing on hands-on project experience to shape how Grant approaches planning, delivery and client relationships.