Client Vision
St Mary’s formed part of the Department of Education Pathfinder programme, upgrading the energy performance of the existing school through improvements to both the building fabric and its services.
The €4.5m retrofit brought together insulation, windows and airtightness works with upgrades to heating, lighting and building controls, providing a coordinated upgrade to the existing school.
The Challenge
School retrofit projects are planned around a defined summer delivery window, with the building ready for the start of the new school year. That makes the work completed before the summer programme particularly important.
Surveys, design coordination, procurement and subcontractor packages can be progressed in advance, allowing the site team to mobilise with a clear sequence of works as soon as the building becomes available.
At St Mary’s, that preparation supported a programme bringing together building fabric improvements with upgrades to heating, lighting and controls across the existing school.
Grant’s Solution & Delivery
Grant plans education projects around the date the school needs to reopen. Pre-construction is used to establish existing conditions, coordinate design information, identify procurement requirements and develop the sequence of works before the summer delivery period begins.
For St Mary’s, the programme incorporated insulation, windows and airtightness alongside mechanical heating, LED lighting and BMS upgrades. Managing these packages under one main contractor provided oversight of the interfaces between the building fabric and services as the works progressed.
Progress, quality and outstanding information were tracked throughout delivery, giving the project team a clear view of each package against the summer programme and supporting coordination through to completion.
Scope of Works
- Building fabric and insulation upgrades
- Window upgrades
- Airtightness works
- Mechanical heating upgrades
- LED lighting
- BMS and controls
- Associated energy-efficiency works
Outcome
St Mary’s received a coordinated upgrade to its building fabric and building services as part of the Department of Education Pathfinder programme, improving the energy performance of the existing school while retaining and upgrading the existing asset.